Deep Foundations for the Salt Lake City International Airport Redevelopment Program
August 28, 2019
During the summer of 2014, the Salt Lake City Department of Airports (SLCDA) broke ground on one of the most complex construction projects in Utah history. In order to keep pace with the demands of the nearly 23 million people that use its facilities each year, the SLCDA initiated a $3.6 billion redevelopment program that will transform the current Salt Lake International Airport into one of the nation's most efficient airports. The first phase of the program features a modernized three-story terminal building, two new concourses, several new parking structures and the longest bridge constructed in Utah all supported by a deep foundation system consisting of over 95 miles of driven steel piles!
Installing this massive deep foundation system by December 2018 was critical to keeping this high-profile program on schedule and setting the stage for its successful delivery. Ralph L. Wadsworth Construction Company, LLC (RLW) was the firm selected to shoulder the burden of getting the project started correctly. Working as a subcontractor to HDJV Construction, a joint venture between Holder Construction and Big-D Construction, RLW overcame a multitude of challenges related to schedule, design, safety and logistics.
Schedule
The schedule for pile driving operations was aggressive and unforgiving. From start to finish, the project required more than 5,300 separate pipe piles (16"×0.5"), and 550 H-piles (14"×102') to be delivered, driven, spliced, welded, cut and poured. (A partial aerial view of the site is in Figure 1.)
The schedule required the team to work year-round and in all types of weather conditions, driving 60 to 80 piles each day. At the peak of the work, RLW had more than 30 construction professionals working at the site, using day and night shifts as well as weekends.
Pile depths and weights
The individual pipe pile lengths ranged from 45 feet to 80 feet per piece (Figure 3), and the weight was 82.8 lb. per foot. Several piles were installed to depths that ranged between 88 to 120 feet, which required the team to splice piles together.
Logistics
This project required 26 different lengths of pile, many in excess of 80 feet. Beyond handling the sheer quantity of pile pieces, their length created challenges for transporting, storing and maneuvering them at the site. Manufactured in California and Mississippi by Skyline Steel, the piles were transported by barges and then by rail to Salt Lake City. Trucks with extra-long beds carried the more than 70-foot-long piles through city streets to the project site, transporting no more than six piles at a time. RLW carefully scheduled deliveries around traffic patterns and managed inventories to minimize the amount of storage space required on-site.
RLW's team also procured and modified specialized pieces of equipment to unload trucks and move piles around the site (as shown in Figure 4). These machines used clamping forks to hold the large piles in place while moving allowing the team to transport them efficiently and, more importantly, safely.
The massive size and scope of the entire construction program together with a single point of site access demanded extensive coordination with other contractors and trades working at the Airport. RLW met with other contractors several times each week to plan deliveries, adjust storage areas and coordinate sequencing details.
Special innovations: Techniques, equipment and materials
Several factors made this 130-acre site unique. First, the soil conditions and geology fluctuated substantially within the vast construction area. Second, the various structures each had specific engineering requirements that called for different pile sizes and lengths. Lastly, some of the work needed to be performed in small areas, either pinched between or immediately adjacent to existing structures still in operation. No two areas were exactly alike, which compelled a customized area-by-area approach to pile driving.
In order to efficiently drive pile in these varied conditions, RLW utilized its full breadth of equipment optimizing equipment strengths to specific challenges. Seven different sized ICE hammers, both hydraulic and diesel, were used according to area soil conditions and proximity to buildings. Six different sized Manitowoc cranes were used, engaging both swinging and fixed leads, to maximize production and safety.
For the work performed immediately next to the existing airport terminal, vibration and noise impacts needed to be minimized to avoid disrupting airport operations. RLW used special equipment and techniques to mitigate these pile driving affects, including predrilling, sound curtains, optimized hammer selection and automated vibration monitoring with real-time text and email notifications if vibrations reached allowable limits.
Many piles were specified to be driven to depths of 120 ft., which required splicing that had to be UT tested. In order to maintain the aggressive schedule and execute high quality splicing operations, the team drove the first (bottom) pile during the day. Night shift crews welded the second (top) pile together with the first (as shown in Figure 2). Day shift crews finished driving the extended pile the following day. By performing all the welding operations at night, RLW was able to keep the hammer continuously working through daylight hours to maintain the schedule. This efficient approach allowed the team to continue installing 60 to 80 piles each day.
Unique application of piles
Part of this project included extending an existing concrete tunnel proposed to provide underground transportation for passengers between terminals. The tunnel had a bottom elevation of 28 feet below grade, and since the water table was only five feet below grade, an earth shoring and dewatering system was required to expose the work area.
A significant challenge arose when the geotechnical engineer-of-record calculated that the required dewatering efforts would cause the tunnel to settle about seven inches the structure's allowable settlement tolerance was less than half an inch.
The owner and the design team developed several designs to support the existing tunnel and limit the settlement due to dewatering. The frontrunner was a proposed solution to use micropiles drilled through the tunnel's six-foot-thick mat footing floor. The significant drawback to this solution was that it would damage the tunnel's existing waterproofing and expose the tunnel to potential long-term water-penetration issues.
Although this work was outside RLW's original scope, its on-site management team learned of the problem and seized the opportunity to find a better way using driven piles. RLW's team proposed driving 20 piles to a depth of 120 feet on both sides of the existing tunnel. Beams would then be placed on top of the driven piles and would span overtop the tunnel. These beams would then be connected to the tunnel's lid using threaded rods and welded connections. Hydraulic jacks installed between the beam and driven pile would allow the system to adjust to compensate for any differential settlement that might develop along the length of the tunnel. The strength of RLW's driven pile method was that it was quick, simple, flexible and required no modifications to the existing footing below the water table mark.
After reviewing RLW's solution, the owner and design team scrapped the other designs and selected the driven pile option, concluding that "it offered the best value to the project" (Figure 7 depicts this solution). The implemented solution worked beautifully.
Construction problems and creative solutions
Part of the redevelopment program included a pedestrian bridge to connect the new terminal to the existing airport facilities. The original plans for this bridge used 36-inch and 48-inch caissons drilled to depths approaching 80 feet. Once installed, the plans called for a 10-foot to 13-foot concrete column to then be poured as a separate component on top of the drilled shaft.
Challenges for the general contractor arose in the constructability of such a design in the middle of an operating airport. Situated between the airport's busiest domestic terminal and the international terminal, the structure spanned over a central walkway, the staff bus stop, the long-term parking bus stop and the airport's retail delivery access point. In order to minimize disruptions to daily operations and reduce safety risks to passengers at the airport, this work had to be completed at night, with working hours restricted to an eight-hour window between 9 p.m to 5 a.m. Moreover, the actual production hours were further limited by the requirement to mobilize all equipment to the work area, perform the work, clean, demobilize the equipment to a storage area and reinstall safety devices all within the eight-hour window.
Once again, RLW saw an opportunity to improve this design concept using driven piles. Its team met with the general contractor, airport, geotechnical engineer, and structural engineer and proposed revising the design to use continuous 36"×0.5" and 48"×0.5" driven steel piles instead of caissons and columns. This structurally acceptable design allowed the foundation work and column work for the bridge to be completed as one unit, cutting the construction time by half. The new piles were driven and vibrated to depth, and were left extending 10 to 12 feet above the existing ground elevation. Beyond its schedule advantage, this approach also had other benefits to the project. First, it did not require holes to remain open for any length of time, thereby eliminating the public safety risk of the proposed design. Second, it afforded the use of dynamic testing methods, which immediately verified the pile capacities and allowed the embedment length to be reduced by 33 percent saving the project significant cost savings. RLW installed two piles per night with minimal disruption to airport customers and operations. (Construction of the pedestrian bridge is shown in Figure 8.)
Innovative project management
Typically, a new airport would be built at a separate location either across town, similar to Denver's approach with its international airport, or on a parcel adjacent to an existing airport. The new Salt Lake City International Airport is unusual because it is designed to be constructed in phases on the existing footprint. This presented numerous challenges that required a high level of coordination between the construction team and airport operations.
RLW's pre-construction support for the foundation design of the pedestrian bridge and the dewatering and earth shoring of the tunnel demonstrates a spirit of true partnership. Participating in the design process was not part of the firm's scope or contract, yet RLW's project team repeatedly demonstrated a willingness to share ideas openly and a passion for thinking creatively. This collaborative approach was consistent with the Construction Manager at Risk (CMAR) contracting method used by the airport and the general contractor, which allowed the construction team to provide input during design.
During construction, RLW's management team adopted a proactive management approach for scheduling, pricing and coordination. They coordinated with the owner's construction and QA/QC teams on quality requirements, hold points and materials testing and certification. They coordinated with the FAA to ensure that all piling and foundation operations met federal guidelines including those for crane heights and temporary lighting for night construction work. Using weekly schedule updates, the team pre-planned all operations, using night shifts and weekends to complete key activities on time.
This proactive pre-planning approach paid off during the summer months when temperatures rose to over 100 degrees during a critical time when significant field welding was required. The heat posed a major safety risk to the workers dressed in full leathers. Even cooling vests and shaded work areas were insufficient to protect the welders from heat exhaustion. Night work was discouraged at the site due to its potential for negative impact on flight operations. Exceptions required a detailed plan and routinely took over two months to approve. Fortunately, RLW's management team identified the risk of approval delays as part of an internal brainstorming session held well before the start of work. As a contingency, the team had submitted several alternate work plans to the airport for review, and worked through the approval process for each, not knowing if they would ever be needed. One of these included a directional lighting plan that allowed limited work at night. Armed with an approved work plan, RLW had the flexibility to separate the crews, leaving some to drive pile in the day and moving others to weld at night. Not only did this mitigate the safety risks from the heat, but the cooler temperatures also expedited UT weld testing and ultimately allowed the project to gain 17 days on the schedule.
Conclusion
In summary, RLW met the challenge of this difficult job through the use of cost saving value engineering methods in the design and construction of the deep foundation systems. Both client and owner appreciated RLW's quality of work and their ability to meet a demanding project schedule in a safe and productive manner.
When overall excellence is discussed concerning large deep foundation projects, partnering with the owner and stakeholders must be at the forefront. RLW's relationship with its owners and general contractors is second to none due in large part to the open communication and close collaboration maintained throughout the project. The project NCR log never carried more than five items at any one time and project completion showed less than 25 total issues logged. The success of this project is a testament to the close collaboration within the project team is an excellent example of how the simplicity, durability and flexibility of driven steel piles still reigns supreme in the deep foundation marketplace.